MCIAT chartered drawings · Fixed fees across all 33 London boroughs and Essex

Free 2026 London Planning ReportSoundproofing Drawings

Red-brick Victorian mansion blocks with white sash windows on a quiet London street, cars parked at the kerb
Drawings · London & Essex

Soundproofing Drawings for London and Essex Homes

Converting a house into flats, adding a floor above a shop, or fixing a noise complaint after the fact all raise the same question in London and Essex: how do the walls and floors between two homes resist sound under Part E, and how do you prove it to building control. A timber-floored Victorian terrace in Lambeth and a between-the-wars semi in Chelmsford fail the sound test in different ways, and the drawings have to say which failure you are designing against.

  • MCIAT chartered technologists
  • Fixed fee from £1,600
  • The 33 London boroughs granted 86% of 24758 householder applications
  • Drawings in about 7 days

Free soundproofing drawings quote

Tell us the postcode and the project. A fixed fee and a route answer within one working day.

No obligation · No spam · Reply within 1 working day

The short answer

Soundproofing drawings are the building-regulations details that show how a new or existing separating wall, floor or stair will resist airborne and impact sound under Approved Document E. For a flat conversion they set out each build-up and junction so building control can approve the design before the pre-completion sound test confirms it on site.

This page sets out what soundproofing drawings actually show, when Approved Document E applies to a project, and which route, a pre-completion test, a registered Robust Detail or a bespoke build-up, suits a conversion rather than a new-build block. It draws on Approved Document E and the Robust Details Ltd guidance directly, not on a manufacturer's product sheet.

What are soundproofing drawings?

A soundproofing drawing is a construction detail, not a specification note. It shows the layers in a separating wall, floor or stair as a section, dimensions the gaps and cavities that make an independent lining or a floating floor work, and cross-references each build-up to the plan so an inspector can see exactly where it applies. Approved Document E covers three situations that need this level of detail: separating elements between dwellings, the lighter requirement for internal walls and floors inside a single house, and reverberation in the common parts of a block of flats.

Building control reviews the drawing before work starts, not after. A product data sheet for a soundproofing quilt tells the inspector what the material can do in a laboratory; it says nothing about how that quilt sits against your particular party wall, joists and skirting. The drawing is where the general performance of a product becomes a specific, checkable construction.

When does Part E apply to your project?

Turning a house into flats is a material change of use, and it brings Part E requirements even where no new wall gets built, because the existing construction now separates two homes rather than one. A loft conversion or extension inside a single house is different: the internal walls and floors there follow the lighter requirement for new walls to bedrooms and WC rooms and new internal floors, and it does not reach back into existing construction that a conversion is built around. Houses in multiple occupation sit in between; whether Part E applies depends on whether the rooms count as rooms for residential purposes, and government guidance treats that as a case-by-case question rather than a fixed rule.

One point catches out landlords fixing a noise complaint after the event: the Building Regulations are not retrospective. A tenant's complaint about noise through an existing floor is not, on its own, a building control matter. Upgrading that floor anyway is worth drawing to the same standard as a new conversion, but it stays a voluntary job rather than a compliance one.

What building control needs to see on the drawings

Building control wants every separating wall, floor and stair marked on the existing and proposed plans, not just named in a specification. Each separating floor needs a section through the full build-up, from the finished floor above to the ceiling below, with the resilient layer or independent ceiling drawn to scale. The junctions are where inspectors look hardest: floor to external wall, floor to party wall, wall head to ceiling, and stair to the room below, because sound gets round a poorly detailed junction as readily as it gets through a wall.

Service penetrations matter as much as the main construction. Pipes, ducts, downlights and back-to-back sockets all need a shown location and a sealing detail, because an unplanned downlight through an independent ceiling undoes the separation it was meant to provide. Where new construction adds mass to an existing floor or wall, the drawings flag the load for the structural engineer, since an upgraded separating floor is heavier than the one it replaces.

What the drawing set contains

A soundproofing drawing set for a London or Essex conversion runs to a few consistent parts. Existing and proposed floor plans mark up every separating element. Sections through each separating floor, wall and stair show the full build-up at scale. Junction details resolve the flanking paths at every wall head, floor edge and party wall. A specification schedule names each layer, its minimum thickness and mass, so nothing gets substituted on site without it showing up against the drawing. A short note records the intended compliance route, whether that is a pre-completion sound test or a registered Robust Detail, so the tester and the inspector read the same plan.

We draw this pack for a fixed fee, with free redraws until building control is satisfied, because the design tends to move once the structural engineer has confirmed what the existing floor can carry.

Robust Details, pre-completion testing or a bespoke detail?

There are three routes to demonstrating that a separating wall or floor performs, and a conversion is usually locked into one of them before the drawings are finished. Robust Details registration only applies to new-build attached houses and flats, registered with Robust Details Ltd before work starts and built exactly to the published handbook detail; the scheme's own guidance is explicit that it does not cover a converted or renovated building. Pre-completion testing is the default for a conversion: an accredited tester visits once the flats are essentially complete, and the results go to building control. A bespoke detail, drawn to an Approved Document E treatment or a manufacturer's system with test evidence, suits an awkward building where neither of the other two routes fits cleanly.

How the sound test works on a small conversion

A test is organised in sets, and the number of individual tests in a set depends on whether the project has separating walls, separating floors, or both; a small conversion with one of each still needs a full set covering both elements, and getting access to enough finished flats to test properly is worth arranging with the other households early. A site with only one pair of converted flats is tested regardless of its size, and larger conversions are tested at a set rate across each group of similar layouts rather than as a single sample for the whole building. Testing to corridors, stairwells and hallways is not done in the same way, not because that junction is exempt, but because those spaces give unreliable results: their complex shape and volume make a standard sound measurement unrepresentative. The wall between a flat and the corridor still has to be built as a separating wall, and the flat's entrance door needs to be a heavy or acoustically rated door to match it. The common parts get a separate treatment instead, an absorption requirement under Approved Document E's reverberation guidance (E3), which is a different test from the airborne and impact measurements taken between flats.

Timing matters as much as the construction. Approved Document E asks for the building to be essentially complete except for decoration, so the test does not wait for decorating to finish. Soft floor coverings are the exception that does matter: the test is normally carried out before carpets and other soft coverings go down, though a bonded resilient covering that forms part of the floor construction itself can be in place. A failed test means remedial work, a second test, and sometimes a look at neighbouring rooms built to the same construction, which is exactly the scenario the drawings exist to prevent by getting the build-up right before anyone starts building.

Why conversions fail the test, and how the drawings prevent it

Most failures trace back to a handful of repeated mistakes, and each has a drawn answer. A lining fixed straight to the party wall instead of held clear on an independent frame carries sound through every fixing; the drawing dimensions the clearance so the site cannot miss it. A resilient layer bridged by a skirting board or a badly placed fixing loses most of its value; the section shows the layer running past the skirting rather than stopping at it. An unplanned downlight or a back-to-back socket punched through an independent ceiling after the drawings were issued undoes weeks of careful build-up; naming the fitting positions on the drawing removes that guesswork on site.

Product substitution is the other recurring cause. A board or a quilt swapped for something similar but lighter changes the mass the whole design relies on, and the specification schedule exists so a site manager can check what was actually installed against what was drawn.

Converting a Victorian or Edwardian house: floors, walls and stairs

London and Essex both carry plenty of the same housing stock behind this problem: timber-floored terraces and semis with lath-and-plaster ceilings, single-brick spine walls, and a stair that ends up doing a separating job between two new flats. Approved Document E's guidance for this kind of building starts with the existing construction, not the new layer on top of it. Gaps in existing floorboards get sealed, and where boards are due to be replaced anyway, Approved Document E sets a minimum thickness for the new ones rather than requiring sound boards to be swapped out. A lath-and-plaster ceiling is kept where it still satisfies the fire requirements in Part B; Approved Document E's own ceiling treatments are written for ceilings that aren't lath and plaster, so a ceiling that doesn't meet the fire requirement gets upgraded to a construction the guidance actually covers.

Only once that remedial work is done does the acoustic treatment go on: an independent ceiling or a floating floor above, an independent lining to the spine wall, and a soft covering with an independent ceiling below where a stair separates two flats. Ceiling heights are worth checking early, because these build-ups add real depth and a low Victorian upper floor can end up close to the minimum comfortable height. In a conservation area or a listed building, the standard is still to improve performance as far as is practical, taking the conservation officer's advice on how the work sits alongside the building's character, and a notice giving the tested values is fixed in a conspicuous place inside the building for the occupants, rather than the requirement being set aside altogether.

Do loft conversions and extensions need soundproofing drawings?

Inside a single house, a new wall to a bedroom or a WC room, or a new internal floor created by a loft conversion, follows a lighter laboratory-tested standard than a separating wall between two dwellings. It doesn't apply to a wall with a door in it, to an en-suite wall, or to existing walls and floors that a conversion is built around rather than newly built. A terrace loft conversion raises a slightly different question: where the party wall continues up into the new roof space, it is still a separating wall between two homes, and the treatment that applies lower down the house generally needs to continue with it.

A detached Essex house extending into the roof has no adjoining dwelling to separate from, so the party wall question doesn't arise at all. A semi is different: its single party wall carries up into the new roof space rather than stopping at the original ceiling line, so that one wall still needs the separating treatment even though the house has only one neighbour rather than two. The drawings still record the internal wall and floor requirement for the new bedrooms in either case, since building control checks it regardless of whether a neighbour is affected.

Comparing the three routes
RouteWhat it needsWhen it suits
Robust DetailsA new-build plot registered with Robust Details Ltd before work starts, built exactly to the published handbook detailNew-build attached houses or flats; never a conversion, extension or refurbishment
Pre-completion testingAn accredited tester on site once the flats are essentially complete, with results passed to building controlEvery house-to-flats conversion in London or Essex, and any new-build that did not register a Robust Detail
Bespoke detailAn Approved Document E treatment or a manufacturer's system with test evidence, drawn with its junctions and checked for added structural loadPeriod houses with awkward flanking paths, and listed or conservation-area buildings where a standard treatment cannot be applied in full
A building-control sheet showing a separating wall junction between two flats, with the independent lining, cavity and mineral wool named at scale. — a real sheet from a DrawingsDirect soundproofing drawings package
A building-control sheet showing a separating wall junction between two flats, with the independent lining, cavity and mineral wool named at scale.
Check your route

Does this need planning permission where you are?

Route check · your area

Listed building?
Conservation area?
Likely permitted development — no planning applicationNeeds checking
  • A single-storey rear extension up to 4 m deep on a detached house, or 3 m on any other house, is Class A permitted development subject to the height and materials conditions.
  • One or more constraints are unknown — we check the council's registers as part of the free appraisal.
  • Where permitted development applies, a lawful development certificate proves it for lenders and buyers.

Sources: GPDO 2015, Schedule 2, Part 1 · Planning Portal — common projects · Building Regulations 2010 — when approval is needed

This is a first-pass indication from the national rules, not planning advice for your property. Your council's registers, any Article 4 schedule and the exact dimensions decide it — the free appraisal checks all three before we recommend a route.

Confirm it with a free appraisal

Householder planning decisions across London

All 33 London boroughs, 2025 Q2 to 2026 Q1.

Householder applications decided24,758
Granted21,185
GrantedEngland 90%86%

Source: Ministry of Housing, Communities and Local Government (PS2 district planning application statistics). Open Government Licence v3.0 Extracted 2026-09-22.

What you receive

Explore a real drawing set

Building control pack sheet from a DrawingsDirect package, showing the details a council checks

What the council checks on this sheet

  • Wall, floor and roof build-ups with U-values (Part L)
  • Fire separation and escape (Part B)
  • Drainage runs and connections (Part H)
  • Structural notes referencing the engineer's calcs
FAQ

Soundproofing Drawings — FAQs

Do I need soundproofing drawings for a flat conversion?+
Yes. Turning a house into flats is a material change of use under the Building Regulations, and Approved Document E applies to every wall and floor that now separates two homes. Building control expects that construction to be drawn, not described, and it will usually be tested before sign-off.
What drawings does building control need for sound insulation in a flat conversion?+
It wants every separating wall, floor and stair marked on plan, a section through each build-up, and the junctions where flanking happens resolved in detail. A specification schedule naming each layer's thickness and mass, plus a note on the intended testing route, completes the pack.
Does Part E apply to existing dwellings?+
The Building Regulations are not retrospective, so Part E does not reach into a home that isn't undergoing work. It applies once you carry out building work, or a material change of use such as converting a house into flats, because that work brings the separating elements into scope.
Can I use Robust Details for a conversion?+
No. Robust Details Ltd registers new-build houses and flats only; its own guidance rules out registering a converted or renovated building. A conversion instead relies on pre-completion testing, or a bespoke detail drawn and tested where the building is too awkward for a standard construction.
What happens if you fail a Part E sound test?+
The tester reports the shortfall, and remedial work follows before a retest, usually to the resilient layer, the lining or a flanking path that let sound through. Where several rooms share the same construction, building control may ask for more of them to be checked once the fix is proven on the first.
Free Fixed Quote

Get a fixed fee for soundproofing drawings

Postcode, project, and any sketch you have. We reply with a route and a price within one working day.