Three-storey stock brick Victorian villas with bay windows, the type of neighbouring house a schedule of condition records
Schedule of Condition

Schedule of condition for party wall work in London

A schedule of condition is a dated, photographed and written record of a neighbour's property, made before your building work starts. If a crack appears later, both sides can see whether it was already there. It costs £245 for each adjoining property, and the check after the works is £150.

Fixed fee from £245 · all prices

Check your property — free

60 seconds now. A fixed, no-obligation quote back within one working day — and we’ll tell you if you don’t even need planning.

No obligation · No spam · Reply within 1 working day

Prefer to talk it through?

What a schedule of condition is for

Building work near a neighbour can cause cracks, and a dispute about damage often turns on one question: was it already there? The Act makes the building owner liable to compensate any adjoining owner and any adjoining occupier for loss or damage resulting from work under the Act. A dated record means you pay for what you caused, and not for what was there before.

It protects the neighbour too. They hold the same evidence, so there is nothing to argue about later and nobody has to rely on memory.

Schedule of Condition

from £245

Every price is the full fixed fee you pay. No VAT is charged. Council application fees are paid to the council separately.

What you get

  • A visit to the adjoining property, with the neighbour's agreement
  • Dated photographs of walls, ceilings, floors and existing cracks
  • A written description of each room and the boundary wall
  • A copy for you and a copy offered to the neighbour
  • A check after the works, compared against the record
  • A set you can hand to a surveyor if a dispute arises
How a schedule of condition runs
  1. Agree the visit

    We arrange access to the neighbour's rooms next to the work, at a time that suits them.

  2. Photograph and write up

    Each room and the shared wall, with existing cracks and damp marks noted and dated.

  3. Copies issued

    You keep one; the neighbour is offered one, so both sides hold the same record.

  4. Check after the works

    We revisit and compare the property against the record, and note anything that changed.

What the record contains

We photograph and describe the rooms and structure on the neighbour's side that sit next to your work: the shared wall, the ceilings below and above it, floors, the chimney breast, the outside of the party wall in the loft or garden. Existing cracks are measured and photographed with a scale, so a later change is visible. Each photo is dated.

The set is written for a surveyor to read: room by room, with the date and who was present. It is a record of what we saw, not a structural opinion.

Long terrace of dark red brick houses with flat-roofed bay windows and roof dormers, climbing a hill, with a white van parked in front
Red-brick terrace with white-painted gables and finials

A party structure notice goes out at least two months before work begins, and an excavation notice at least one month before you begin to excavate.

Party Wall etc. Act 1996 s3(2)(a) (source wording: "served at least two months before the date on which the proposed work will begin"). www.legislation.gov.uk

Who needs one, and when

Any time you serve a notice that affects an adjoining owner's property, it is worth having one, particularly for excavation. Under section 6 a notice of adjacent excavation is needed when you dig within 3 metres of a neighbour's building or, where cutting a 45 degree line, within 6 metres. The deeper and closer the dig, the more a record matters.

It is also used at the start of a lease, where a tenant records the condition of a property so that they are not charged for existing wear when they leave. The method is the same; only the audience differs.

Per adjoining property, and the check after the works

The fee is £245 for each adjoining property, because each is a separate visit and record. A semi-detached house with one neighbour needs one; a terrace end-of-row may need one on each side.

When the work is finished, the check after the works costs £150. We return, compare each room with the record, and list anything that has changed. If nothing has, you have a signed-off comparison to show the neighbour or a surveyor.

DrawingsDirect sample planning sheet with proposed plans and elevations at 1:100 and a site plan at 1:500
Sample drawing

How it fits with the notice

A schedule of condition is not a notice, and it does not replace one. Serve the party wall notice first, because the notice is the legal step, and have the record made before any work begins, ideally within the notice period. A party structure notice goes out at least two months before work begins, and an excavation notice at least one month before you begin to excavate.

If a dispute does arise, the surveyors will want the record. See party wall surveyor referral for how that works, or the party wall services overview to check whether the Act applies to you at all.

Data

Sources

Every figure on this page, where it comes from and a link to the original.

FigureSourceLink
compensate any adjoining owner and any adjoining occupierParty Wall etc. Act 1996 s7(2) (source wording: "The building owner shall compensate any adjoining owner and any adjoining occupier for any loss or damage")www.legislation.gov.uk
3 metresParty Wall etc. Act 1996 s6(1)(a) (source wording: "within a distance of three metres measured horizontally from any part of a building or structure of an adjoining owner")www.legislation.gov.uk
6 metresParty Wall etc. Act 1996 s6(2)(a) (source wording: "within a distance of six metres measured horizontally from any part of a building or structure of an adjoining owner")www.legislation.gov.uk
two monthsParty Wall etc. Act 1996 s3(2)(a) (source wording: "served at least two months before the date on which the proposed work will begin")www.legislation.gov.uk
one monthParty Wall etc. Act 1996 s6(5) (source wording: "at least one month before beginning to excavate")www.legislation.gov.uk
FAQ

Questions people ask

Does the Party Wall Act require a schedule of condition?
No. The Act does not require one. It is good practice because the building owner is liable for damage resulting from the work, and a dated record shows what was already there.
Do I need one for each neighbour?
Yes, one for each adjoining property. The fee is per property, since each needs its own visit and record.
What if my neighbour will not let us in?
We cannot enter without their agreement. We can record what is visible from your side and the outside, and we note in the record that access was refused.
Is the check after the works compulsory?
No. It is an optional extra, but without it you have a before record and nothing to compare it with.
Can I use one at the start of a lease?
Yes. A dated record of a property's condition at lease start is the same document, and helps settle deposit or dilapidations arguments at the end.